My notes show 6 weeks for me. Stone coping and tile was pretty fast after gunite, but the concrete deck guys plus cleanup took a month and we only had 200 sqft of deck. Throw in Thanksgiving for another dead week. But again, I had a pretty smooth experience all together.
Here's my notes if anybody gives a shit. Not included is the meetings with builders, etc...just from making the decision and telling builder to go.
Permit application - July 20-24 - 1 week
Permit from City - Aug 12 - 3 weeks
Wait to start - Aug 17-Sept 14 - 4 weeks
Excavation - Sept14-25 - 2 weeks
Rebar, plumbing, equipment, elect inspection - Sept 28-Oct1 - 1 week
Gunite - Oct 16 - 2 weeks
Gunite cure - 1 week
Stone, tile - Oct 26-30 - 1 week
Deck forms - Nov 10-12 - 2 weeks
Deck poor - Nov 19 - 1 week
Cleanup - Nov 20
Thanksgiving - 1 week
Pebble - Nov 30-Dec1
Fill, fence repair - Dec 2-3 - 1 week
Lawn, irrigation repair - Dec 10-11
Sundek - Jan 6-7